New piers required for the bifolds and the old blockwork not up to the job.
Noggings to repair the landing floor progressing.
Delayed full start to wall removal, but plumber was on-site for an early start. Letters dropped to neighbours. Radiators have been removed/capped. Relocation of under-floor copper pipework ready for installation of vertical wall mounted rads. Refilling of system and bleeding of rads created a few problems although system up and running at close of play. This caused the cementing of new exposed pipework to be put off until Day 2.